Galliford Try Total Energy Management Service

Implement a total energy management service for two secondary schools, reducing costs and carbon emissions.

Energy audit, Carbon Management Action Plan (CMAP), monitoring equipment installation, BMS service contract, insulation, equipment optimization, behavior change program.

Optimised BMS system, 39,591,137 liters of water saved (40% reduction), 20% electricity and 35% gas savings, 1,890 tonnes of CO2e saved.

Project

Galliford Try manage the facilities for two private finance initiative secondary schools. In a time of rising energy costs, the schools were keen to reduce running costs and carbon emissions and to engage building users. Anthesis supported Galliford Try with the application of a total energy management service for the schools to manage utilities, provide cost reductions and ongoing support, investment and advice.